Search
Close this search box.

 York

Fifth Grove

Construction Updates

Fifth Grove –Completed June 2024

Construction at Fifth Grove is complete! Looking incredible both inside & out, tenants are already moving in to these apartments and our investors are seeing great returns!

Fifth Grove Construction Update – February 2024

The building is now fully watertight, with roofing and window installations complete. First fix M&E is finished on upper floors, plastering has started on the top floor, and ground floor M&E is being finalised. External rendering will progress when weather permits. Gas installation awaits LCC permission, and water installation depends on postal address registration, expected shortly. External works will begin alongside internal second fix once services are installed.

Fifth Grove Construction Update –January 2024

In Block A, air and acoustical testing has been completed, electrical supply and heating are operational, and laminate flooring installation is underway. Block B has energised electrical supply and heating, with joinery first fix and decoration in progress. In Block C, mechanical first fix is complete, walls and ceilings are closed, and ground floor plastering is finished. Externally, most underground ducting, kerb lines, formation levels, and surface water drainage have been installed and connected to drains.

Fifth Grove Construction Update – November 2023

The construction at Fifth Grove is coming along well. In Block A, kitchen installations are underway, with shower trays and WHBs arriving Thursday, and tiling scheduled to begin on 2nd October. In Block B, ground floor plaster skimming is set to finish this week, mist coats are planned for next week, and kitchen deliveries are expected on 9th October. The first floor has windows, electricals, and plumbing mostly complete, with skimming at 20%. Block C roof tiling is ongoing, and screeds are set to commence on 2nd October. For externals, the substation is complete, and HV is installed on-site, but off-site HV connections await legal agreements.

Fifth Grove Construction Update –September 2023

Good progress has been made at Fifth Grove. For Block A, floor screeds have been completed, scaffolding is down on one level, and drylining is underway. Roof tiling has been completed for Block B, and Masonry is underway for Block C.

Fifth Grove Construction Update – February 2023

Construction at Fifth Grove is progressing well; the demolition works have been completed, ground works have commenced, and foundations for blocks A & B have been laid.