All units are on track to be completed in April with communal areas 3/4 complete Scaffolding to be removed within the next two weeks once lighting pads are fitted and cladding complete The ground floor and first floor units are complete save for some internal doors and minor snagging, all kitchens and bathrooms are now installed except for 3 bathrooms and 11 kitchens on the 2nd floor. Communal areas to be painted and handrails to be fitted to staircases in coming weeks. Communal area carpets to be fitted first week of march. Est Completion Date – April 2024 Valuation appointments access will be permitted from mid-march